Using Value Stream Mapping to Reduce Overhead Labor

Download White Paper: Using Value Stream Mapping to Reduce Overhead Labor

Abstract

Lean Six Sigma is used to improve quality, increase productivity and reduce cycle time. However, most of the applications to increase productivity are dealing with direct labor. We have extensive experience using Lean Six Sigma to improve direct labor productivity in Distribution (order selectors), Hospitals (nurses), Financial Services Companies (application processors and accountants) and Factories (production employees). When demand decreases, as it did recently during the Great Recession of 2007 – 2009, direct labor can be reduced in proportion to demand. However, indirect labor (also called Overhead Labor) is often harder to reduce.

This paper will demonstrate how Value Stream Mapping can be used to identify areas of excess indirect / overhead labor within a company.

Background

This Plastics Manufacturing Company was caught in the Great Recession of 2007 – 2009. They were operating profitably through the mid 2000’s. In 2008 their customers cut back orders dramatically. One large customer was an auto assembly plant that closed permanently.

They reduced direct labor in proportion to demand. But they still had unacceptably high indirect / overhead labor expenses. Instead of simply cutting these positions, they wanted to use Value Stream Mapping to identify where they could reduce costs. In addition to the short term cost reduction, they also viewed this as an opportunity to realign their indirect labor staff with their 24 hour a day production operations.

Value Stream Mapping

A Value Stream Map is a high level view of a process. This process can be an entire supply chain, the operations within a department or the steps to complete an order.

In addition to the high level view, a Value Stream Map seeks to quantify what the people and machines in the process are doing. Are they adding value to the product or service, are they waiting or are they doing non-value added tasks?

By gathering this data by time study we can see within the process how much of the time people and equipment are working and adding value for the customer, working but doing non value added tasks or waiting and doing nothing.

Plastics Manufacturing – Value Stream Major Steps

The scope of our Value Stream Mapping began at scheduling orders for production and finished when manufactured goods were put in inventory to be shipped to customers. Note, we did not include order-entry or shipping. We decided to keep this scope to the production operations of the company.

Within these steps we time studied:

  • Material Handlers – Moved raw materials to the Mixing department, from Mixing to Molding and finished product to inventory
  • Mixers – Prepared the plastic raw materials for molding
  • Utility Workers – Did miscellaneous tasks as part of the order
  • Lead Operator – Oversaw other Operators
  • Operator – Checked quality of product coming off of the machine and packed product that was not robot-packed
  • Set-Up Technician – Set up machine to make a new part, involving mold changes and pick & pack robotics
  • Supervisor – Overall shift manager who also scheduled orders
  • Inspector – Did first part inspection and set up inspection station for part changeover
  • Machine utilization – The time the machine was producing parts versus its 24 hour per day, 7 day per week, 365 day per year availability

We time studied each of these roles as they touched an order. This was a high volume and high mix production company so there were numerous orders to time study. The variables in orders were part complexity and count. We performed enough time studies to account for this variation.

What Value Stream Mapping Showed Us

  • Inspectors are only 50% utilized
  • Utility Workers are very under-utilized and have no immediate link to an order
    • Giving them the ability to “float” around the plant
  • Lead Operators are under utilized and also “float” around the plant
  • 2nd and 3rd Shifts are understaffed with Supervisors, process expertise and prep (Mixing) employees
    • There were staffed to accommodate people’s desire to work on day shift versus the needs of production
  • They are not working the molding machines very hard and have too many machines

For each of the roles above we calculated their utilization for a full day. This was done via the simple calculation below:

People Utilization = Average Minutes per Order x Average # of Orders per Day ÷ Effective Time per Person

The results were shocking. We identified operations that were dramatically underutilized. Because these people weren’t directly linked to an order, they were allowed to “float” around the facility. Many times we saw them talking and disrupting direct people, sitting in an office or didn’t see them at all!

For the machines, the results were equally shocking. This company clearly was not “working the assets”. Operating Equipment Efficiency (OEE) is a simple measure that can be benchmarked across any company and industry. It is the sell-able output from a machine divided by the theoretical output on a 24 hours per day, 7 days per week, 365 days per year basis.

OEE doesn’t care that a company may not want to work weekends or 3rd shift. This measure also doesn’t care if you don’t have enough demand to keep machinery busy. It only looks at how much of the available capacity we are using to make sales.

On this basis, this company had too much machinery. Note, that much of this data is pre-recession demand. Only 3 – 4 machines were operating at a high OEE utilization. Most machines were used less than 50% of their availability. About five machines, which produced less complex parts, were operating at about 30%. This data created a very difficult action item to evaluate selling some of the machines and outsourcing some customer orders to companies that specialized in less complex parts.

Staffing Rebalancing

This chart shows how indirect positions were either eliminated or rebalanced on 2nd and 3rd shifts based on the utilization data.

Operating Equipment Efficiency – Machine Utilization

Machine # 13, 04 and 08, which operate at high OEE utilization

Machine 22, 12, 23, 14, 15 and 02 operate at very low OEE utilization

Results

  • Eliminated Lead Operators
  • Eliminated Floor Workers
  • Reduced Inspectors
  • Improved shift performance

As seen on the chart on Page 5, they were able to eliminate 5.5 overhead labor positions. Most of these positions were people who had very low utilization and “floated” around the facility because they were not directly linked to an order. Lead Operators were moved back to being Operators. Floor Worker jobs were eliminated, with this work being done by Operators.

There was great debate about eliminating Inspectors, and the affect it would have on quality. However, in the end they realized that quality is not “inspected-in”; it happens at production and is the responsibility of Operators.

This cost reduction helped them survive the recession, but in addition they found improved shift performance by moving highly skilled people to 2nd and 3rd shift, which was lacking support. This further reduced downtime costs and improved on time delivery of product to the customer.

The result of this project was difficult on employees. We were moving people from 1st shift to 2nd and 3rd, which is a difficult transition. In other places we permanently eliminated positions at the company, forcing these people to go back to being Operators.

However, the ownership did not just do a mass layoff. They invested to cut costs where it would not impact the Customer, but would actually improve off-shift performance.

Learn more about our Value Stream Mapping Services.

Client Voice

What Clients Say

View All Testimonials

"If you are looking for someone to help drive improvements, create repeatable processes and mentor younger staff in your facility then reach out to Supply Velocity. Your expertise and dedication have driven significant im..."

Tim Donohoe

COO, Chemline

"I am thrilled to provide this testimonial for Supply Velocity and their outstanding work in implementing Lean Warehouses and processes at Crescent Parts & Equipment through the COVID pandemic. With their data-first focus..."

Josh Cole

Director of Supply Chain, Crescent Parts & Equipment

"For several years we have worked with Supply Velocity to support us with their expertise on Lean Operations and Supply Chain Management. Supply Velocity has helped us implement Lean, improve our inventory systems, and ed..."

Lorenza Pasetti

CEO, Volpi Foods

"Supply Velocity is driving instrumental change in our inventory management processes. This is critical for us to be competitive in a supply chain environment with numerous disruptions. They are making change happen, whic..."

Jim Carroll

Executive Vice President Operations, Schaeffer Manufacturing

"In a time of volatile supply chain disruption, Supply Velocity is helping us develop Demand and Supply Planning processes to proactively tackle these new challenges. They are genuine partners, working with our team, faci..."

Jane Thrasher

Vice President of Supply Chain, Horizon Hobby

"Mitch Millstein and his team helped guide our shop fabrication division in the re-layout of our custom pipe and steel fabrication facility when we moved into a new building. It is not only the results but how he helped...."

Geoff Gross

President, Gross Mechanical

"In 2015 we began working with Dr. Mitch Millstein to optimize our inventory locations supporting e-commerce and in-store inventory needs. From this work we developed a new omni-channel warehousing and inventory plan that..."

Rob Bowers

Vice President of Strategy, Total Hockey

"Myerson engaged Supply Velocity, specifically Ray Davis to visit our plant in Trinidad to conduct a two day assessment of our production procedures and provide us feedback on areas for improvement and where applicable, a..."

Lee Hartwell CPA

Plant Manager, Myerson Tooth

"Supply Velocity has provided the technical expertise and political capital to move our project forward. They have just the right amount of push and the right amount of support. Supply Velocity has helped us make real cha..."

David Walters

President, Hy-C

"Our experience with Supply Velocity was one of the best values we have ever had from a consulting project. Cyril Narishkin brought a structured lean methodology, invaluable experience and engaging facilitation skills to..."

Mike Howard

CEO, Aspeq

"Supply Velocity has helped Clean succeed in a number of ways. First, they provided the education that kicked off our Lean Process Improvement journey. They also facilitated a number of large supply chain and process impr..."

Jeff Lazaroff

Senior Vice President, Clean Uniform

"We engaged with Supply Velocity to help us embed process improvement at all levels of the business. Our team learned from Mitch to let the data drive decisions, to use Lean tools to help us see our processes critically a..."

Dionne Dumitru

COO, Weekends Only

"Supply Velocity gave us the tools to analyze our business and processes based on the facts and numbers versus our perceptions. Our common quote was "Let the numbers lead us". The key for our organization was how quickly..."

Ned Lane

President, CeeKay Supply

"We used Supply Velocity to rethink our sales process. By analyzing the entire process we found wasted time in our Sales, Admin and Operations departments. Streamlining this process created extra time for each Sales Rep,..."

Jeff Reitz

Vice President, Central States Bus

"Supply Velocity created visibility within our Assurance Services Group... visibility of performance, Client-service, employee satisfaction and processing time. Using the Supply Velocity System, Audit Report Cycle time is..."

Fred Kostecki

Partner-In-Charge, Assurance Services, Rubin Brown

"Supply Velocity's Lean Six Sigma System has given us new tools to help improve our sales performance. We have learned new ways to analyze our business which makes problem solving more accurate and has made us better lead..."

Rachel Andreasson

Executive Vice President - Marketing, Wallis Companies

"The role of the Erie Insurance Marketing Department has been evolving over the past several years - from a support role to a more critical role of driving growth in our organization. Because of our increased workload and..."

Karen Rugare

Director of Marketing, Erie Insurance

"Isolating a problem, finding short, and long term solutions with measurable results is what was promised and results is what was delivered by Supply Velocity. Upon launch of the Lean Six Sigma Selling System, we knew mor..."

Mark A. Presker

General Manager, Architectural Millwork of St. Louis

"In the spring of 2003, the St. Louis Area Chapter of the American Red Cross engaged Supply Velocity, Inc. to perform a study and make recommendations to streamline office processes, maximize cash flow in purchasing and w..."

Joe White

CEO, American Red Cross - Saint Louis Chapter

"We are using Supply Velocity's Lean Six Sigma methods to analyze a variety of processes including rationalizing SKUs (stock-keeping-units). By using math to evaluate SKUs we took some of the emotion out of our decisions...."

Mark Kelso

Director of Process Improvement, Save-A-Lot

"Anheuser-Busch Precision Printing had been implementing Lean Operations on our own for the past two years. We needed to move faster and partnered with Supply Velocity, Inc. Through Supply Velocity, Inc.'s mathematical wo..."

Rich Lavosky

General Manager, Anheuser-Busch Precision Printing

"C&R was struggling with labor productivity. The construction crews were often missing materials that they needed to do their work. This caused significant idle time. Supply Velocity, Inc. and C&R used value stream mappin..."

Tom Kuthe

V.P. Construction Operations, C&R Mechanical

"Your process encourages this group to work together, better communicate and have fun doing it."

George Edinger

President, C&R Mechanical

"Closure Medical recently completed a major reorganization in order to enhance our ability to rapidly create innovative medical devices. We hired Supply Velocity to help us map out the process and service flows of the new..."

Gabe Szabo

Vice President, Product Development, Closure Medical - A Division of Johnson & Johnson

"We are pleased that Essex selected Supply Velocity, Inc. as our Lean Implementation Partner. At one facility, we have saved over $350,000 in work-in-process inventory, reduced throughput time from 2 weeks to minutes and..."

Terry Etter

Vice President of Operations, Essex Medical Systems

"In thirty years of hiring consultants, Supply Velocity, Inc. was the first to tell me what they were going to do, set a price they stuck to and substantially exceed my expectations. I have recommended them to friends and..."

Bill Gilbert

President, Fusion Coatings

"Many thanks to all three Supply Velocity presenters. I think you guys took a very difficult time for learning and capitalized on everyone's time and training needs. I truly hope this helps your business as this was a con..."

Mark Holdinghausen

VP of Operations, DEMA Engineering

"We used Supply Velocity on our Warehouse optimization project. One of the key characteristics of Supply Velocity is that they listened to our requirements and provided a clear path for our Warehouse processes using lean..."

Haris Tokalic

President, Grand Rock, Inc.

"I’d recommend Supply Velocity to organizations looking for a hands‑on, data‑driven warehouse assessment with actionable outputs - particularly those dealing with operational change, new systems, or scaling challenges."

Jayson Wickenkamp

Senior Vice President, Image Solutions